From our Team telecon
Wednesday, August 2:


* Project items for IMPACT

- The Phase A Technical Report was delivered
  to GSFC on July 31. 

- The Phase A Cost Report is due August 31.
  Budgets for the Phase A Cost Report should have
  all the contents of a formal budget but do
  not need to be signed off by your institution
  (yet) until after Project review of the Report.
  Dave Curtis will be sending templates and other
  instructions to all who are requesting NASA funds.
  For Travel assume Project meetings every 6 mos
  w/ alternating location at GSFC and Team insts.
  Dave Curtis will supply schedule of assumed
  Project meetings, Team meetings, and Reviews
  at SSL or GSFC. Please respond to his requests,
  and try to get your detailed information in by
  August 23 so it can be merged.

- Meetings to note: An Internal Assessment Team
  review of the Phase A Technical Study is now
  planned at GSFC Aug 9. Dave Curtis will summarize
  our Phase A Techical Report there and also attend 
  the Stored Command Meeting at APL August 10.

- Project is having IMPACT telecons every week
  on Tuesday at 2:30PM eastern (GSFC) time.
  Dave Curtis will alert you if you should
  participate

- STEREO Project will have a new GSFC Manager in Sept.
  (Abby Harper will manage the entire STP Program) 
  There may be schedule slips due to budget, all the
  extra peer reviews, and general competition for DSN
  according to Project.


* Instruments

- SEP needs to resolve remaining FOV issues
  and bracket design issues with APL on
  the redesigned spacecraft (Tycho)

- Boom/Astromast redesign to be worked at
  UCB (Dave)

- Remember to think about needed covers  

* Other

- Tycho will support Contamination Committee
  activities for IMPACT

- Dave Curtis needs information on what is
  spent during Phase A and Bridge by GSFC
  team members (533s type information) for
  the record


*******************************************

IMPORTANT DATES

Aug 31 Full Cost Report due
Oct 31 End of Phase A + Bridge


*******************************************

Websites to Check periodically for updates 

http://sprg.ssl.berkeley.edu/impact
http://sprg.ssl.berkeley.edu/impact/dwc
http://sprg.ssl.berkeley.edu/~jgluhman/stereo
https://sd-forum.jhuapl.edu/stereo/