From our Team telecon Wed February 12, 2003: * Project items for IMPACT - Current issues: Presentation on schedule rebaseline was given to GSFC Program Management Council by Project on Feb 10. Critical milestones for all mission investigations and spacecraft will be reviewed by this board again in 2 months. Our Milestones and top level rebaselined schedule can be seen in the IMPACT part of the Mission CDR presentation (see below). Please check your milestones. - Schedule/Meetings: Mission CDR will be Feb. 18-20 at APL. Included 1 hr IMPACT presentation can be seen on the usual impact "dwc" web site (url at bottom). SWAVES CDR held Feb. 11-12. - Spacecraft: All ICDs needed by mission CDR - Budget: Tight for '03. * Instruments - High priority IMPACT action items for next weeks include power converters, SEP detectors STE DAC replacements and parts tests - Boom Design: T-V chamber options for deployment tests need to be discussed again. Also Strategy for removing boom from top of mission risk list. - Mag parts/screening issues need to be worked - Status of magnetic cleanliness items: Is SECCHI still a possible area of concern? - Ground strap design being done by Paul Turin at UCB. (status?) - There are currently weekly or biweekly SEP telecons on Thursdays, and periodic BOOM and IDPU meetings at UCB. All-team telecons are now once/month: 2003 IMPACT Wed. telecons, provisional dates are second Wednesdays of each month at 9AM Pacific (exceptions for major meeting weeks, also subject to changes announced by email) -------------------------------------------- March 12, April 9, May 14, June 11, July 2(early due to SHINE meeting), Aug 13, Sep 10, Oct 8, Nov 12, Dec team meeting - Phase C Progress Report information will be collected by Dave prior to the 15th of each month. Will now include milestone tracking. * Other - Peter Schroeder (peters@ssl.berkeley.edu) completed the Data Management Plan draft. Need to continue discussion of a common data format for archive purposes in response to CDR panel feedback. - selected Helios 1/2 data are available for browsing and download- as a STEREO in-situ prototype set- at the URL http://sprg.ssl.berkeley.edu/htbin/impact/HeliosData.pl ****************************************** IMPORTANT DATES Feb 18-20 '03 MISSION CDR Nov '05- Launch ******************************************* Websites to Check periodically for updates http://sprg.ssl.berkeley.edu/impact http://sprg.ssl.berkeley.edu/impact/dwc https://sd-forum.jhuapl.edu/stereo/