Dear IMPACT Team, From our Team telecon Wednesday, July 5: * Last Project telecon action items for IMPACT (please give to Dave Curtis on request): - Project has redesigned the spacecraft and as a result wants a shorter (by 12 in.) IMPACT fixed mast. Dave Curtis to work this. - Budgets for Phase A Cost Report should have all the contents of a formal budget but do not need to be signed off by your institution (yet) until after Project review of these. For Travel assume Project meetings every 6 mos w/ alternating location at GSFC and Team insts. Dave Curtis will supply schedule of Team mtgs. - Project to have IMPACT telecons every week on Tuesday at 2:30PM eastern (GSFC) time. Dave Curtis can tell you how to participate * Instruments - SEP needs to resolve remaining FOV issues with APL on redesigned spacecraft (Tycho) - Boom/Astromast redesign to bw worked at UCB (Dave) - Remember to think about needed covers * Other - Tycho will support Contamination Committee activities for IMPACT (Therese Errigo at GSFC will chair it) - Please remember that the Phase A Technical Report is due July 31. ******************************************* IMPORTANT DATES Jul 31 Phase A Report due Aug 31 Full Cost Report due Oct 31 End of Phase A + Bridge ******************************************* Websites to Check periodically for updates http://sprg.ssl.berkeley.edu/impact http://sprg.ssl.berkeley.edu/impact/dwc http://sprg.ssl.berkeley.edu/~jgluhman/stereo https://sd-forum.jhuapl.edu/stereo/