From our Team telecon Wednesday, March 7, 2001: * Project items for IMPACT - IMPACT Boom/SWEA/STE Peer Review occurred at UCB March 6. No major issues were raised. Dave Curtis will contact CoIs with some followup questions. Next IMPACT Peer Review is SEP/MAG at GSFC on April 19. Dave Curtis will post the presentations on our website. - Project wants IMPACT to support (in person or by phone) all spacecraft coordination meetings at 10AM Thursdays at APL. They have asked Robert Ullrich, our boom engineer, to participate this Thursday in a mechanical/structural discussion Dave Curtis will ask IMPACT team members to help support these as appropriate - Budget: The new UCB (Phase B) contract startup is currently under negotiation with the GSFC. We are currently in a no cost extension until March 31. (Remember that this budget will need revision at some point, so UCB will be requesting subcontractors to make the post-Phase A negotation changes.) - STEREO Project will hold separate PDRs for the spacecraft and instruments in late September. Dates are still TBD * Instruments - During Phase B IMPACT is required to make monthly updates to schedule and Risks. Dave Curtis will set up a template and we will use our team telecons and email to make most regular updates - SEP needs to resolve remaining FOV issues and bracket design issues with APL on the new spacecraft configuration (Tycho) - SEP needs to work on a detailed schedule with Dave Curtis as input to the IMPACT master schedule (Tycho, Alan, Dave) - Dave Curtis to provide project with more detailed drawings of SWEA - Boom Design: Robert Ullrich is working on the boom prototype design, and must respond to Project re. a shorter stowed unit. Project also wants stacer samples to show others re. potential glint * Other - Next IMPACT Team Meeting Sunday Morning, June 3, in Boston. This is after the Boston Spring AGU meeting and before the next STEREO SWG meeting at UNH on June 4-5. - Dave Curtis still needs to know what is being spent by GSFC IMPACT team members (533s type information) for the record ******************************************* IMPORTANT DATES Mar 31 End of current contract NCE April 19 SEP/MAG Peer Review at GSFC June 3 Next IMPACT Team Meeting in Boston June 4-5 Next STEREO SWG at UNH ******************************************* Websites to Check periodically for updates http://sprg.ssl.berkeley.edu/impact http://sprg.ssl.berkeley.edu/impact/dwc https://sd-forum.jhuapl.edu/stereo/