From our Team telecon Wed Mar 10, 2004: * Project items for IMPACT - Current issues: New GSFC PM contact info: nicholas.g.chrissotimos@nasa.gov phone 301-286-5108 Please track the new Project charts at the site http://sprg.ssl.berkeley.edu/impact/dwc/Schedules/ and also the critical milestones in IMPACT Critical Milestone Chart.HTM Inform Dave Curtis of any changes to your items. - Spacecraft: launch date 02/06 - Budget: Project has requested budget replan with schedule update. - Schedule: IMPACT deliveries still on old schedule (Oct 2004 FMs delivery) - Data Management: Peter Schroeder has requested data set samples (status?) * Instruments - Rebudget plans needed at UCB and GSFC by March 12 - Need to think about I&T staffing support (possible local to APL help?) - SEPT underwent some of its environment tests- and TRR. Vibe test door anomaly addressed. - Actel issue persists. - Still issues with SEP detectors and mounts - Boom: FMs in construction. - Mag cleanliness issues are still being worked. - There are currently weekly or biweekly SEP telecons on Thursdays, and periodic BOOM and IDPU meetings at UCB. All-team telecons are now once/month: 2004 IMPACT Wed. telecons, provisional dates are second Wednesdays of each month at 9AM Pacific -------------------------------------------- nominal dates: 04/14,05/12,06/09,07/14,08/11,09/08,10/13,11/10, Dec Team Meeting 12/17 or 18 - Phase C Progress Report information will be collected by Dave prior to the 15th of each month. Will now include milestone tracking. ****************************************** IMPORTANT DATES March 22, '04 SWG in Boulder April 20, '04 I&T meeting at APL April 21, '04 Ops meeting at APL June '04 Pre-environ. Review delta (@Caltech) Oct 7 '04 FM1 delivery Oct 28 '04 FM2 delivery Feb 11 '06- Launch ******************************************* Websites to Check periodically for updates http://sprg.ssl.berkeley.edu/impact http://sprg.ssl.berkeley.edu/impact/dwc https://sd-forum.jhuapl.edu/stereo/