From our Team telecon Wednesday, May 2, 2001: * Project items for IMPACT - Schedule: New launch date is Nov-Dec '05. Instrument PDR is still Sept. 4-6 at APL, but spacecraft PDR is moved to December. Phase B now ends in March '02. Confirmation Review in March will be preceded by another independent review of STEREO (involvement of IMPACT in this is unknown). See the new schedule on Dave Curtis' IMPACT website. - Budget: The new UCB (Phase B) contract startup paperwork is now back at GSFC for their approval. We are still in a no cost extension Bridge Phase until May 31. Dave Curtis needs new cost/schedule feedback on extended, flat profile from Caltech and Maryland (see your emails). - Project continues to hold spacecraft coordination meetings Thursdays 10AM at APL. Telecon lines are available. - Next IMPACT Peer Review on IDPU and Software, planned for June 13 at UCB, may be moved due to anticipated HESSI launch on June 7 * Instruments - SEP needs to resolve remaining FOV and bracket design issues with APL - SEP needs to resolve SIT/TOF definition issue - MAG needs a mag cleanliness appointee at APL (person also needs to cover ESC) - STE needs to resolve its newly discovered FOV issue - IMPACT Merged schedule (Boom suite, SEP, IDPU) still needs to be made - Thermal designs (first order) to Project by mid-May. Project to provide assistance. - Boom Design: needs to be finalized and surface conductivity addressed. - During Phase B IMPACT is required to make monthly updates to power, mass, schedule and Risks. * Other - Dave Curtis will be involved in HESSI launch activities during team meeting, and SWG. - Next IMPACT Team Meeting Sunday, June 3, in Boston (~8:30am-2pm at a Midtown Hotel, 220 Huntington Ave.- look for a sign saying AGU or STEREO in the lobby to locate meeting room). An overhead projector and coffee will be available. - Dave Curtis still needs to know what is being spent by GSFC IMPACT team members (533s type information) for the record ******************************************* IMPORTANT DATES May 31 end of current UCB contracts NCE June 3 Next IMPACT Team Meeting in Boston June 4 Next STEREO SWG at UNH June 13(?) IDPU/Software Peer Review at UCB Aug 2 Wrapup/ I&T Peer Review at UCB ******************************************* Websites to Check periodically for updates http://sprg.ssl.berkeley.edu/impact http://sprg.ssl.berkeley.edu/impact/dwc https://sd-forum.jhuapl.edu/stereo/