From our Team telecon
Wed May 12, 2004:


* Project items for IMPACT

- Current events: 

  STEREO Mission Manager Odendahl has been appointed
  for post-launch project maagement at GSFC 

  New GSFC PM contact info: nicholas.g.chrissotimos@nasa.gov 
  phone 301-286-5108

  Dave Curtis attended the project I&T workshop in late April.

  Project to visit UCB on 05/18 to discuss schedule. Send
  inputs/comments on schedule issues to Dave.

  Next SWG planned for Sept 28-30 at APL

  Please track the new Project charts at the site
  http://sprg.ssl.berkeley.edu/impact/dwc/Schedules/
  and also the critical milestones in
  IMPACT Critical Milestone Chart.HTM
  Inform Dave Curtis of any changes to your items.

- Spacecraft: launch date 02/06

- Budget: Project has requested budget replan with schedule update. 
          Due on 05/28.

- Schedule: IMPACT deliveries still on old schedule (Oct 2004 FMs delivery)

- Ops and Data Management: Peter Schroeder is preparing a
		   simulated data processing sequence on
		   a sample data file and may ask for input.
		   Peter and Dave attended the APL Ops workshop
		   in late April. Peter attended a Spice Kernel
		   workshop at JPL last week.

* Instruments

- More Technical help sought for FM work at UCB. 
  Please contact Dave Curtis with suggested sources
  of temporary NASA-qualified help.

- GSFC looking into possible I&T staffing support
  (e.g. local to APL help?)

- independent door problems on SEPT and STE being worked

- Actel issue persists.

- SEP HET detectors and mounts issues persist

- Boom: FMs in construction. TV test schedule impacted
  somewhat by STE door problem.

- Magnetics meeting held on May 12 focused on
  compensation magnets installation on spacecraft

- There are currently weekly or biweekly SEP telecons
  on Thursdays, and periodic BOOM and IDPU meetings at UCB. 
  All-team telecons are now once/month:

  2004 IMPACT Wed. telecons, provisional dates
  are second Wednesdays of each month at 9AM Pacific
  --------------------------------------------
  nominal dates:
  06/09,07/14,08/11,09/08,10/13,11/10,
  Dec Team Meeting 12/17 or 18
  
- Phase C Progress Report information will be collected
  by Dave prior to the 15th of each month. Will now include
  milestone tracking.

******************************************

IMPORTANT DATES

May 19 '04 Contamination Control meeting 2pmET
May 20 '04 EMC meeting 2pmET
June 14 '04 SWEA/IDPU TRR
June '04 Pre-environ. Review delta (@Caltech)
Sept. 28-30 SWG@APL
Oct 7 '04 FM1 delivery
Oct 28 '04 FM2 delivery
Feb 11 '06- Launch

*******************************************