From our Team telecon Wednesday, May 16, 2001: * Project items for IMPACT - Schedule: New launch date is Nov-Dec '05. Instrument PDR is now a week later: Sept. 11-13 at APL. Spacecraft PDR has moved to early December. Phase B now ends in March '02. Confirmation Review in March. See the new schedule on Dave Curtis' IMPACT website. Project has promised to review our PDR deliverables list next week to advise us of requirements. - Budget: The new UCB (Phase B) contract startup paperwork is still back at GSFC for their approval. We are still in a no cost extension Bridge Phase until May 31, and may need one more. - Project continues to hold spacecraft coordination meetings Thursdays 10AM at APL. Telecon lines are available. This Thursday's topics are software protocol for spacecraft interface (IDPU issues), plus emulator and GSE matters related to this. - Next IMPACT Peer Review on IDPU and Software, planned for June 28 at UCB (new date). "Wrapup" pre-PDR Peer Review still nominally Aug. 2 at UCB. * Instruments - SEP needs to resolve remaining FOV and bracket design issues with APL - MAG needs a mag cleanliness appointee at APL (person also needs to cover ESC) - STE needs to resolve its newly discovered FOV issue - IMPACT Merged schedule (Boom suite, SEP, IDPU) still needs to be made - Thermal designs (first order) to Project by mid-May. Project to provide assistance. - Boom Design: needs to be finalized and surface conductivity addressed. - During Phase B IMPACT is required to make monthly updates to power, mass, schedule and Risks. * Other - Dave Curtis will be involved in HESSI launch activities during team meeting, and SWG. Use email to contact him. - Next IMPACT Team Meeting Sunday, June 3, in Boston (~8:30am-2pm at a Midtown Hotel, 220 Huntington Ave.- look for a sign saying AGU or STEREO in the lobby to locate meeting room). An overhead projector and coffee will be available. SWG follows on June 4 in New Hampshire. ******************************************* IMPORTANT DATES May 31 end of current UCB contracts NCE June 3 Next IMPACT Team Meeting in Boston June 4 Next STEREO SWG at UNH June 28 IDPU/Software Peer Review at UCB Aug 2 Wrapup/ I&T Peer Review at UCB ******************************************* Websites to Check periodically for updates http://sprg.ssl.berkeley.edu/impact http://sprg.ssl.berkeley.edu/impact/dwc https://sd-forum.jhuapl.edu/stereo/