From our Team telecon Wednesday, November 1, 2000: * Project items for IMPACT - Project has asked that IMPACT present its budget descope plan, to meet the post Phase-A Report cost cap for phases A-D, next Tuesday. SEP and Boom Suite groups are working to meet comparable reduction goals. Unfortunately, all non-hardware items such as pre-launch science and EPO will be hard-hit. Janet will contact those affected this week. SEP and Boom Suite team budget discussion will occur end of this week. - Schedule/Budgets: No-Cost extensions to the end of November should be in effect. UCB subcontractors please let us know if you have not been contacted. Phase B should start up in December based on the Phase A Report Budgets, but signed-off copies have not yet been requested, and of course the Phase A Report Budgets will be altered. - Peer Reviews. We have requested to delay the requested Software Review. Project agreed but would still like answers to the questions Dave Curtis distributed. SEP please respond after the budget matters settle down. Dave has already submitted answers for IDPU. - ITAR: LOAs have been sent out from NASA. Project asks that our non-US CoIs contact their LOA recipients in case there are questions about the Project or the LOAs. Drafts of Technical Assistance Agreements (TAAs), between JHUAPL and our non-US CoIs, have been sent out for comment. Comments Janet has received have been forwarded to APL. Please let Janet know your disposition on these agreements if you have not already done so (even if you cannot sign such a document). * Instruments - Boom Design studies are underway because of the role they play in the budget strategy. Ask Dave Curtis for a copy of the new boom design proposal if you are interested in the current plan. - SEP needs to resolve remaining FOV issues and bracket design issues with APL on the redesigned spacecraft (Tycho) - ESC and Solar Array situation is still under study at Maxwell Technologies. Contact Davin Larson for information. Project decision to relax conductivity requirements on the solar arrays has essentially been made, in part to resolve budget problems. An updated, revised and expanded document on ESC, EMC and MAG cleanliness by Ogilvie, Acuna and Manning is available. Contact Keith, Janet or Dave Curtis for a copy. * Other - Tycho will support Contamination Committee activities for IMPACT - Dave Curtis still needs to know what was spent during Phase A and Bridge by GSFC team members (533s type information) for the record ******************************************* IMPORTANT DATES Oct 31 End of Phase A + Bridge Nov 31 End of no-cost extension for the above Dec 12 next IMPACT team meeting at UCB SSL Dec 13-14 STEREO SWG at UCB SSL ******************************************* Websites to Check periodically for updates http://sprg.ssl.berkeley.edu/impact http://sprg.ssl.berkeley.edu/impact/dwc https://sd-forum.jhuapl.edu/stereo/