From our Team telecon
Wednesday, November 1, 2000:


* Project items for IMPACT

- Project has asked that IMPACT present its
  budget descope plan, to meet the post Phase-A  
  Report cost cap for phases A-D, next Tuesday. 
  SEP and Boom Suite groups are working to meet
  comparable reduction goals. Unfortunately,
  all non-hardware items such as pre-launch
  science and EPO will be hard-hit. Janet
  will contact those affected this week.
  SEP and Boom Suite team budget discussion
  will occur end of this week.
   
- Schedule/Budgets: No-Cost extensions to
  the end of November should be in effect. UCB
  subcontractors please let us know if you have
  not been contacted. Phase B should start up
  in December based on the Phase A Report
  Budgets, but signed-off copies have not
  yet been requested, and of course the Phase A
  Report Budgets will be altered.

- Peer Reviews. We have requested to delay the
  requested Software Review. Project agreed but
  would still like answers to the questions Dave
  Curtis distributed. SEP please respond after
  the budget matters settle down. Dave has
  already submitted answers for IDPU.

- ITAR: LOAs have been sent out from NASA.
  Project asks that our non-US CoIs contact
  their LOA recipients in case there are questions
  about the Project or the LOAs. Drafts of
  Technical Assistance Agreements (TAAs), 
  between JHUAPL and our non-US CoIs,
  have been sent out for comment. Comments
  Janet has received have been forwarded to
  APL. Please let Janet know your disposition
  on these agreements if you have not already
  done so (even if you cannot sign such a
  document).


* Instruments

- Boom Design studies are underway because of    
  the role they play in the budget strategy.
  Ask Dave Curtis for a copy of the new boom
  design proposal if you are interested in
  the current plan.

- SEP needs to resolve remaining FOV issues
  and bracket design issues with APL on
  the redesigned spacecraft (Tycho)

- ESC and Solar Array situation is still
  under study at Maxwell Technologies.
  Contact Davin Larson for information.
  Project decision to relax conductivity
  requirements on the solar arrays has essentially
  been made, in part to resolve budget problems.
  An updated, revised and expanded  document on
  ESC, EMC and MAG cleanliness by Ogilvie, Acuna and
  Manning is available. Contact Keith, Janet or
  Dave Curtis for a copy.


* Other

- Tycho will support Contamination Committee
  activities for IMPACT

- Dave Curtis still needs to know what was
  spent during Phase A and Bridge by GSFC
  team members (533s type information) for
  the record

*******************************************

IMPORTANT DATES

Oct 31 End of Phase A + Bridge
Nov 31 End of no-cost extension for the above
Dec 12 next IMPACT team meeting at UCB SSL
Dec 13-14 STEREO SWG at UCB SSL

*******************************************